EXECUTIVE SUMMARY
The Ski Dubai Remedial Works project showcases Spider Access’s expertise in delivering complex rope access maintenance and structural repair services in one of the UAE’s most unique and challenging environments. Located within the Mall of the Emirates, this high-profile project involved internal and external repairs to steel structures, concrete mega columns, and insulated systems—all carried out in extreme conditions ranging from sub-zero indoor temperatures to 45°C outdoor heat.
Through strategic planning, IRATA-certified technicians, and industry-approved materials, Spider Access completed the project ahead of schedule with zero disruption to operations and full compliance with safety and quality standards.
Project: Ski Dubai Remedial Works
Location: Mall of the Emirates, Dubai, UAE
Client: Majid Al Futtaim Properties
Main Contractor: Spider Access Cladding & Building Cleaning LLC
Duration: 14 Months (Completed 25 Days Ahead of Schedule)

SCOPE OF WORK
Spider Access was selected to carry out highly specialized rope access maintenance and remedial repair services at Ski Dubai—one of the world’s most iconic indoor ski resorts. The project involved restoring key infrastructure elements while navigating complex operational and environmental conditions. All work was executed with minimal disruption, using IRATA-certified rope access techniques and suspended scaffolding systems. This large-scale remedial project included:
• Internal and external steel structure repair and repainting
• Concrete mega column restoration and application of protective coatings
• Glycol leakage repair in temperature-sensitive zones
• Corrugated sheet repair and painting in the ski dome underbelly
PROJECT GOALS
The Ski Dubai remedial project was driven by a clear set of performance and quality objectives focused on infrastructure restoration and long-term resilience. The following goals were established to ensure both structural enhancement and minimal disruption:
• Restore structural integrity and aesthetic finish of indoor and outdoor steel elements
• Improve performance and durability of critical concrete columns
• Address glycol leakages impacting insulation and facility performance
• Maintain high-quality standards while working in extreme conditions
• Meet deadlines aligned with Ski Dubai’s operational calendar
CHALLENGES
Executing complex remedial works at Ski Dubai required overcoming a unique set of operational and environmental challenges. Below are the key challenges faced during the project:
• Extremely harsh working environment (+45°C outside and sub-zero indoors)
• Active facility with limited access windows due to live public operations
• Confined and high-elevation work zones requiring expert rope access technicians
• Tight coordination required with the Mall of the Emirates’ stakeholders
• Zero room for safety compromise in a public, high-risk environment

SOLUTIONS & EXECUTION METHODOLOGY
To deliver high-quality remedial and maintenance services at Ski Dubai, Spider Access implemented a tailored execution strategy designed for high-risk, climate-sensitive environments.
• Deployed specialized suspended scaffolding and rope access techniques for high-reach areas
• Applied temperature- and humidity-resistant coatings for steel and concrete
• Executed work in controlled phases, aligned with Ski Dubai’s operational needs
• Used advanced leak detection and sealing technology
• Maintained strict QA/QC monitoring with daily safety and progress reports

KEY HIGHLIGHTS & ACHIEVEMENTS
To address the technical and environmental complexities of the Ski Dubai remedial project, Spider Access implemented a strategic combination of advanced rope access systems and engineered solutions. Key solutions included:
• Delivered project 25 days ahead of the planned 14-month schedule
• Maintained Zero Lost Time Incidents (LTI) with 117,600 safe manhours
• Completed all rope access repair works without interrupting facility operations
• Saved the client approximately AED 900,000 through value engineering without compromising the quality.
• Received commendation for coordination, quality, and safe execution in an iconic venue
PROJECT TEAM
The success of the Ski Dubai remedial project was made possible by a highly skilled and experienced team specializing in rope access, structural repairs, and façade maintenance. Each member played a critical role in ensuring safety, quality, and timely delivery in one of the UAE’s most challenging and iconic indoor environments. Backed by IRATA certification and a commitment to excellence, the team demonstrated precision, coordination, and industry-best practices from start to finish.

CONCLUSION
The Ski Dubai Remedial Project demonstrates Spider Access’s capabilities in executing complex rope access maintenance and repair in active environments. Delivered with zero incidents and substantial cost savings, this project reinforces Spider Access’s reputation as one of the leading remedial and rope access contractors in the UAE, with deep expertise in façade and structural maintenance for high-risk facilities. The successful completion of the Ski Dubai Remedial Works project reinforces Spider Access’s position as a trusted provider of rope access solutions and structural maintenance services in the UAE.
From concept to completion, Spider Access delivered a fully integrated service — including engineering design, customized solution development, and precise on-ground execution. Despite extreme working conditions and operational constraints, the project was delivered ahead of schedule, with zero safety incidents and significant cost savings for the client. By combining technical expertise, IRATA-certified workmanship, and meticulous planning, Spider Access ensured the long-term integrity and performance of one of Dubai’s most iconic indoor facilities—setting a benchmark for high-level remedial work in active, high-risk environments.